Construction completion guarantee. In order to ensure
the full and faithful completion of all land development activities
related to compliance with all conditions set forth by the Town of
Carmel in its approval of the stormwater pollution prevention plan,
the Town of Carmel may require the applicant or developer to provide,
prior to construction, a performance bond, cash escrow, or irrevocable
letter of credit from an appropriate financial or surety institution
which guarantees satisfactory completion of the project and names
the Town of Carmel as the beneficiary. The security shall be in an
amount to be determined by the Town of Carmel based on submission
of final design plans, with reference to actual construction and landscaping
costs. The performance guarantee shall remain in force until the surety
is released from liability by the Town of Carmel, provided that such
period shall not be less than one year from the date of final acceptance
or such other certification that the facility(ies) have been constructed
in accordance with the approved plans and specifications and that
a one-year inspection has been conducted and the facilities have been
found to be acceptable to the Town of Carmel. Per annum interest on
cash escrow deposits shall be reinvested in the account until the
surety is released from liability.